Problem NO: 9

The total work content for a product assembled on a manual production line is 48 min. The work is\ntransported using a continuous overhead conveyor tha

The total work content for a product assembled on a manual production line is 48 min. The work is

\r\n

transported using a continuous overhead conveyor that operates at a speed of 3 ft/min. There are 24

\r\n

workstations on the line, one-third of which have two workers; the remaining stations each have one

\r\n

worker. Repositioning time per worker is 9 sec, and uptime efficiency of the line is 95%. (a) What

\r\n

is the maximum possible hourly production rate if line is assumed to be perfectly balanced? (b) If

\r\n

the actual production rate is only 92% of the maximum possible rate determined in part (a), what is

\r\n

the balance efficiency on the line?

0  reviews

Suggestions based on the Question and Answer that you are currently viewing

The benefits of buying with AnswerDone:

Guaranteed quality through customer reviews

Access to High-Quality Documents

Our platform features a wide range of meticulously curated documents, from solved assignments and research papers to detailed study guides. Each document is reviewed to ensure it meets our high standards, giving you access to reliable and high-quality resources.

Quick and easy check-out

Easy and Secure Transactions

We prioritize your security. Our platform uses advanced encryption technology to protect your personal and financial information. Buying with AnswerDone means you can make transactions with confidence, knowing that your data is secure

Focus on what matters

Instant Access

Once you make a purchase, you’ll have immediate access to your documents. No waiting periods or delays—just instant delivery of the resources you need to succeed.

$1.49  0x  sold
    (0)
  Add to cart